If major works are planned for your building, you may receive a letter mentioning “Section 20”. It can look daunting, but it’s actually there to protect leaseholders by making sure they’re told about significant costs and given a chance to have their say.
What is Section 20?
Section 20 of the Landlord and Tenant Act 1985 requires whoever is responsible for the building to consult leaseholders before carrying out certain works or entering certain long-term contracts that will be paid for through the service charge.
When does it apply?
Under the current rules, consultation is generally needed for:
- Qualifying works: works where any one leaseholder would pay more than £250.
- Long-term agreements: contracts lasting more than 12 months where any one leaseholder would pay more than £100 in a year.
How does the process work?
For most major works, there are two main stages:
- Notice of intention. Leaseholders are told what work is proposed and why, and have at least 30 days to comment and, in many cases, to suggest a contractor.
- Statement of estimates. Once quotes have been obtained, leaseholders are sent at least two estimates and again have at least 30 days to comment before a contractor is chosen.
Depending on the outcome, a further notice explaining the choice of contractor may also be needed.
What if it isn’t followed?
If the process isn’t followed properly, the amount that can be recovered from each leaseholder may be limited to £250 for those works, unless a tribunal agrees to waive the requirements. That’s why getting the process right matters for everyone, including resident directors.
The key points
- Section 20 makes sure leaseholders are consulted on significant costs.
- It usually applies when any one leaseholder would pay over £250 for works.
- Leaseholders get time to comment at each stage.
- The rules can change, so always check the current requirements before starting.